Dry Wall with Metal C-Stud Frame Installation

For a dry wall with metal C-studs frame, NCR recommends to use a minimum of six toggle anchors and bolts to secure the kiosk to the wall.

The wall must be prepared, mounting holes drilled, and anchors installed before final siting of the kiosk. It is the responsibility of the owning institution to provide the bolts and anchors for the kiosk.

For wall, bolt holes, and anchor details, see Dry Wall Mounting Details.

To install the kiosk to a dry wall, perform the following steps:

1.Install the Wall Bracket to the wall, see To install the Wall Bracket, perform the following steps:.

2.Install the Main Frame, see Due to its weight, installation of the Main Cabinet requires at least two persons..

3.Install the Top Poles, see Installing the Top Poles require the use of a step ladder or a work platform..

4.Install the Signage, see Install an M4 shoulder screw on the bottom signage mounting hole of each Top Pole..

5.Install the Door Assembly, see Installing the Door Assembly.

6.Install the Display, see Installing the Display.

7.Install the Printer, see Installing the Printer.

8.If required, install the PIN Pad terminals, see Installing PIN Pad Terminals.

9.Route the Internal Cables, see Routing and Connecting Internal Cables.

10.Connect the AC Power Cord and LAN Cable, see Routing the AC Power Cord and LAN Cable.

11.Verify if kiosk installation and cable routing are correct, see Verifying Kiosk Installation and Cable Routing.

12.Turn ON the kiosk, see Turning ON the Kiosk.

13.Load the printer with a Paper Roll, see Loading Printer Paper Roll.